Installation of foundations at Galloper wind farm completed two months early

PUBLISHED: 08:59 31 March 2017 | UPDATED: 08:59 31 March 2017

The foundations for the Galloper offshore wind farm being loaded on to the installation vessel Innovation. Picture: GeoSea.

The foundations for the Galloper offshore wind farm being loaded on to the installation vessel Innovation. Picture: GeoSea.

Archant

The construction of the £1.5bn Galloper offshore wind farm has moved into the next phase after the installation of turbine foundations was completed two months ahead of schedule.

The last of the 56 foundations to be installed at the Galloper offshore wind farm. Picture: GeoSea.The last of the 56 foundations to be installed at the Galloper offshore wind farm. Picture: GeoSea.

The first of the 1,200-tonne foundations - made up of a steel monopile and a transition piece - was installed 30km off the Suffolk coast in late December, and the last of the 56 was fitted on Tuesday.

The work was carried out by GeoSea using its Innovation jack-up vessel, which was upgraded to improve installation times, and had been slated to be completed by May.

Galloper project director Toby Edmonds said: “GeoSea have set records with their barn-storming performance on Galloper. To achieve a cycle-time of within a week to collect and install four complete foundations in remarkable and certainly the fastest we’ve seen so far at innogy.

“To do this in winter makes it all the more impressive. The teams from Galloper and GeoSea have combined brilliantly to reach this major milestone completing the foundation installation stage efficiently and safely in such good time.”

The foundations each weigh about 1,200 tonnes and measure 85m long and 7.5m in diameter.

Installation of the 6MW turbines will now begin, with the wind farm expected to be fully operational by spring 2018.

The Siemens turbines are being pre-assembled at the purpose-built assembly base at Peel Ports, Great Yarmouth, where a 120m crane will lift the turbines on to vessels to sail them to the site.

Construction of Galloper is being led on behalf of the project partners by Innogy SE.

Other News

Yesterday, 15:10

Dog owners and their four-legged friends were out in force as a special event showcased an important campaign.

Yesterday, 13:59

It was an idea that started as a doodle in a notebook and ended up as a shed full of wonder.

Yesterday, 13:50

Quick-thinking members of the public rushed to assist an off duty policeman and retired police dog after a shop owner requested help.

Yesterday, 12:03

Around 2,000 cyclists took to the countryside for the Tour de Broads.

Most Read

Monday, August 6, 2018

Searches are taking place for a 12-year-old boy who has gone missing from home.

Read more
Trafalgar College
Saturday, August 18, 2018

Fifteen fire crews fought a large fire on the old Pontins site in Hemsby in the early hours of this morning.

Read more
Norfolk Fire and Rescue Service
Yesterday, 09:19

This aerial photo shows the scale of the damage caused to the derelict former Pontins site in Hemsby.

Read more
Saturday, August 18, 2018

Comedian Jimmy Carr played a show in Great Yarmouth last night - and even had a gag ready for the seaside town.

Read more
Yesterday, 13:50

Quick-thinking members of the public rushed to assist an off duty policeman and retired police dog after a shop owner requested help.

Read more
Norfolk Police

Local Weather

Overcast

Overcast

max temp: 21°C

min temp: 18°C

Show Job Lists

Digital Edition

cover

Enjoy the Great
Yarmouth Mercury

e-edition today

Subscribe

Newsletter Sign Up

Great Yarmouth Mercury weekly newsletter
Sign up to receive our regular email newsletter

Our Privacy Policy