Date set for work on A12 bridge

PUBLISHED: 16:52 11 May 2010 | UPDATED: 17:44 30 June 2010

WORK to maintain the Bascule Bridge on the A12 in Lowestoft is set to start on Sunday 23 May.

The Highways Agency will resurface, repaint and waterproof the bridge and is expected to complete the work in early July.

WORK to maintain the Bascule Bridge on the A12 in Lowestoft is set to start on Sunday 23 May.

The Highways Agency will resurface, repaint and waterproof the bridge and is expected to complete the work in early July.

There will be lane closures overnight with signals controlling traffic in each direction.

There will also be a full closure of the Bascule Bridge over three week nights in June between 8pm and 6am; these dates subject to progress of works and weather conditions.

A diversion will be in place for northbound traffic along the A1117 Bloodmoor Road, the A146 to the Mutford Lock Bridge in Oulton Broad onto the A117, rejoining the A12 at the Tesco roundabout. Southbound traffic will follow the diversion in reverse.

Local traffic will need to follow a northbound diversion off London Road via Pier Terrace, Horn Hill, Waveney Drive and Bridge Road to cross Mutford Lock Bridge, and join the A12 at the top of Katwijk Way.

Southbound traffic will follow the same diversion in reverse.


If you value what this story gives you, please consider supporting the Great Yarmouth Mercury. Click the link in the yellow box below for details.

Become a supporter

This newspaper has been a central part of community life for many years, through good times and bad, serving as your advocate and trusted source of local information. Our industry is facing testing times, which is why I’m asking for your support. Every single contribution will help us continue to produce award-winning local journalism that makes a measurable difference to our community.

Thank you.

Most Read

Most Read

Latest from the Great Yarmouth Mercury